Agenda item
CGI Contract Performance
To follow.
Minutes:
1.1
The Chair welcomed Mr Dickie, Mr O’ Sullivan
and Mr Scully from CGI to the meeting.
There had been circulated copies of the report by Director
Strategic Commissioning and Partnerships that presented key
information with respect to the CGI contract for the final two
quarters of 2021. It provided Elected
Members with key information on the governance of the contract,
updated information on the transformation programme being delivered
with CGI, key performance information with respect to the service
delivery of the contract and a note of key issues associated with
contract management, which included change requests signed in the
quarter.
1.2
Mr Byers advised that key control boards had taken
place and were subject to minutes and audit. All governance arrangements were marked
‘green’ in quarters three and four. With regards to the Transformation Programme,
development work had been undertaken between senior officers and
CGI to develop the strategic digital roadmap which was aligned to
the corporate plan and financial strategy. A number of projects were partway through
completion, while the Mobile Front Line Workers project, to give
lone workers technology for protection, was entering phase
2. Mr Dickie advised that upon the CGI
contract extension, consultation took place on the strategic
digital roadmap incorporating cost-saving and identifying good
work. Work on Mobile Front Line Workers
would support lone workers with recording timesheets and expenses
and to also provide duty of care support for care
workers. Outputs for the information
hub were due to be approved and the first outputs due to take place
in June 2022. Further detail was
provided on progress with Transformation POAP. Mr O'Sullivan advised that Corporate SIP
Implementation progress was marked as ‘red’ as BT were
delayed with changing fibre and modernising telephony which
continued from delays faced in this area of work following the
onset of the Covid-19 pandemic. The
Office 365 workstream progress was also
marked ‘red’ following issues with migrated data and
Access Database links. This
workstream was to be re-scoped and
incorporated within the Transformation programme following
completion of the Database project review. Digital Customer Access had been due to undergo a
re-plan with intent to be incorporated within prioritised
projects. CGI advised that this was in
a positioning of knowing how to take forward. With regards to the bulk Print project having been
marked as ‘red’ to then being marked as
‘complete’ this had been due to Xerox differentiating
between national and international post. Solutions from Xerox were not regarded as suitable
therefore the workstream was closed off
while an alternative programme would be determined. Councillor Thornton-Nicol raised inconsistencies
with regards to End User Device – Curricular workstream with issues raised in Newtown Community
Wing and there not being access to the devices. Mr Dickie advised that this may have been due to
sites being offline with sporadic IT use from caretakers and that
he would follow up on issues raised.
Technical issues had been affecting the MacBooks workstream
however support was in place and the workstream was due to be closed. The AV Solution workstream had been affected by supply chain of
components issues.
1.3
In response to a question about cybersecurity in
relation to the international environment, Mr Dickie advised that
the issue was being built into the strategic roadmap. CGI provided security services. Public Services Network accreditation had been
going well and reaccreditation was due for April 2022. Mr Byers acknowledged the issue of cybersecurity
had been heightened and that regular meetings had been taking place
with the Security Manager for appropriate patches and policies to
be in place.
1.4
It was noted that the Smart Routing workstream had been paused as work was taking place
with the Director Infrastructure and Environment with regards to
widening the scope of the project beyond waste services to
determine a Council-wide solution. The
Weighbridge workstream was due to enter
the implement phase on February 2022.
The Monitoring and Tracking workstream
was cancelled due to solutions not being obtained for the
project. Comino Performance and Uniform
workstream was on hold while feedback
was being assessed. High School WAN
workstream had been affected by
capacity issues related to an incremental rise in portable devices
using the wireless network.
1.5
Mr Scully presented updates on the Service Delivery
section of the report. It had been
regarded that there was excellent service performance continuing
over quarter four. Service Desk
performance had met all key performance indicator targets in
January and Incident and Service Request backlog remained under
control. An IT Health Check had been
carried out across the Council estate to provide a report for
submission to the Cabinet Office as part of Public Services Network
re-certification and remediation had been progressing
steadily. The Happy Signals pilot had
been continuing to drive user satisfaction insight on completed
Service Activity (incidents and work orders) which had initiated a
number of key Service Improvement workstreams to address feedback
provided. Target User Response Rate had
been averaging 2% and had risen to 11.78%.
1.6
Extreme weather events including Storm Arwen took
place over quarter four which required support from CGI for
Emergency Planning and to recover sites affected by power loss and
subsequent technical issues. Challenges
had persisted following the rollout of the Enterprise Mobility
platform to SB Cares staff where technical and process challenges
required additional Service Support to ensure handsets continued to
be available for staff. Initial support
challenges had been resolved and further improvement works were
continuing. Issues had been encountered
regarding the fulfilment of Xerox printer toner replacements due to
worldwide toner and consumables shortages.
1.7
Challenges in Service Performance had been
encountered that originated following the return of pupils to
schools in late August resulting in a significantly large volume of
logged calls and the formation of a service backlog. User satisfaction fell below the key performance
indicator target of 80%. Mr Scully
noted that was the second year in a row that a backlog formed due
to the return to schools and was not acceptable for CGI.
1.8
With regards to the Commercial and Contract
Overview, it was advised that the Tweedbank Office build was due to
be completed by January 2022 and that the lease was due to be
finalised. The CGI fit-out and
habitation of the office was scheduled for July 2022. CGI employed 68 people in the Scottish Borders and
recruitment was planned for five graduate positions, three graduate
apprentices entering from high school, four project delivery roles,
23 service desk members to be based in Tweedbank and ten test
automation engineers to be based in Tweedbank.
1.9 With regard to paragraph 4 of the Minute of the Meeting held on 23 November 2021 Councillor Thornton-Nicol requested an update to her question on the costs of procured HP monitors compared to the model’s sale value on the market.
DECISION
NOTED the update.
Supporting documents:
- Item No. 05 - CGI-Performance - MCGG, item 2. PDF 184 KB
- Item No. 05 - CGI - Major Contract Review CGI - March 2022, item 2. PDF 3 MB